Government >> Capital Construction Projects
Dovercourt Rd Reconstruction
Dovercourt Road Reconstruction including Watermain and Storm Sewer Replacement
Watermain Replacement from Graeber Avenue to Roxborough Avenue, including road resurfacing.
Budget:
$692,000
Construction Timeline:
- Project complete and in one (1) year Maintenance Period
Notice to Residents:
- August 2, 2017 - Notice of Public Information Centre
- November 10, 2017 - Project Notice
- March 27, 2018 - Project Notice - Construction Re-Start
Contact Informati on for the Project:
Town Contact:
- Nic Chevalier, Project Manager, Engineering Division, nchevalier@forterie.ca, 905-871-1600 ext. 2407
Contractor:
- Vic Vatrt Contracting Inc.
- Vic Vatrt, 905-732-2619, vicvatrt@cogeco.ca